Horizontal Directional Drilling

King's North Connection Project HDD

King's North Connection Project HDD

Location

Toronto, ON

Timeline

2017

Methods

Horizontal Directional Drilling

Scope

Michels was subcontracted to provide all labour, equipment and materials required to complete two 36-inch diameter Horizontal Directional Drills (HDDs) on the King's North Connection Project, an 11-kilometre pipeline project.

The Major MacKenzie Drive HDD was 1191 metres long and the Rutherford Road HDD was 1319 metres long.

  • Michels was subcontracted to provide all labour, equipment and materials required to complete two 36-inch diameter Horizontal Directional Drills (HDDs) on the King's North Connection Project, an 11-kilometre pipeline project.