Vancouver City Central Transmission

Vancouver City Central Transmission

Location

Vancouver, BC

Timeline

2011

Methods

Horizontal Directional Drilling, Percussion ramming, Thermal grout installation

Scope

Michels was prime contractor for installation of a power cable duct under False Creek in conjunction with the Vancouver City Central Transmission Project. The duct and its 230 kilovolt transmission line required a 850-metre Horizontal Directional Drill. This was Vancouver's most significant power project in 30 years.

  • Michels was prime contractor for installation of a power cable duct under False Creek in conjunction with the Vancouver City Central Transmission Project.
  • Michels was prime contractor for installation of a power cable duct under False Creek in conjunction with the Vancouver City Central Transmission Project.