Projects

Projects

After photo from using a spray application of geopolymer mortar to rehabilitate of a utility hole.

Sewer and Water Rehab

Ocean Park Trunk Utility Hole Rehabilitation

View Project

Ocean Park Trunk Utility Hole Rehabilitation

Michels Canada completed a 117-metre long, 2,121-mm diameter tunnel as an outfall for a new wastewater treatment plant on Vancouver Island.

Tunneling

McLoughlin Point Wastewater Treatment Plant outfall

BC

View Project

McLoughlin Point Wastewater Treatment Plant outfall

Michels performed a pilot study to rehabilitate a deteriorating segment of 2,642-millimetre diameter sanitary sewer, approximately 30 metres long.

Sewer and Water Rehab

16th Ave Sanitary Sewer Rehabilitation

ON

View Project

16th Ave Sanitary Sewer Rehabilitation

Michels constructed a 36.2 km (22.5-mile), 30-inch pipeline for the Thornbury section of the Liege Lateral Loop 2.

Directional Drilling

Liege Lateral Loop 2

BC

View Project

Liege Lateral Loop 2

Michels completed 49.6 km natural gas pipeline constructed in Ontario's HydroOne corridor.

Mainline Pipeline

GTA Mainline

ON

View Project

GTA Mainline

Michels built a 148-metre long, 1.8-metre diameter tunnel under the Mary Hill Bypass, a major four-lane highway in the Vancouver metropolitan area, to house a 1.5-metre diameter water main.

Tunneling

Port Mann Main No. 2

BC

View Project

Port Mann Main No. 2

The parallel tunnels both run a length of 1500m at a below ground depth of approximately 14m in Saskatoon.

Tunneling

McOrmond Drive Sanitary & Sewer

SK

View Project

McOrmond Drive Sanitary & Sewer

Michels installed a new 500 metre crossing of NPS 30 pipe beneath the river using horizontal drilling technology (HDD).

Directional Drilling

Moberly River Crossing

BC

View Project

Moberly River Crossing

Michels Canada performed an emergency horizontal directional drill (HDD) of 469 metres. The project was a 5-string bundle of 4-inch, 8-inch and three 12-inch pipes.

Directional Drilling

Pouce Coupe River Crossing

BC

View Project

Pouce Coupe River Crossing

Michels was the Prime Contractor on the FortisBC Coastal Transmission System Project in the Lower Mainland of British Columbia.  The 11 kilometre project consisted of 36-inch and 42-inch new pipe construction in a heavily urban environment.

Direct Pipe

FortisBC Coastal Transmission System (CTS)

BC

View Project

FortisBC Coastal Transmission System (CTS)

Michels was subcontracted to provide all labour, equipment and materials required to complete two 36-inch diameter Horizontal Directional Drills (HDDs) on the King's North Connection Project, an 11-kilometre pipeline project.

Horizontal Directional Drilling

King's North Connection Project HDD

View Project

King's North Connection Project HDD

Michels installed Seven 42-inch heavy wall pipeline trenchless crossings.

Directional Drilling

Northern Courier Crossings

BC

View Project

Northern Courier Crossings

Michels drilled a 966-metre, 36-inch hole under the North Saskatchewan River to simultaneously install a 24-inch welded steel pipeline segment and two strands of 1 1/4-inch polyethylene conduit containing fiber optic cables.

Directional Drilling

North Saskatchewan River

AB

View Project

North Saskatchewan River

Michels completed a Microtunneling project for the city of Edmonton.

Tunneling

Big Lake W14

AB

View Project

Big Lake W14

Michels completed three Horizontal Directional Drills (HDD) and one Direct Pipe installation as part of the Cold Lake South Mainline Loop, an NPS 42 bitumen pipeline originating at the IPF LaCory Facility north of Bonnyville, Alberta to the IPF Facility in Hardisty, Alberta.

Direct Pipe

Cold Lake South Mainline Loop HDD

AB

View Project

Cold Lake South Mainline Loop HDD

Michels used HDD to complete a 800 metre of 12-inch pipe installation under the St. Lawrence River.

Directional Drilling

St. Lawrence River Crossing

ON

View Project

St. Lawrence River Crossing

Michels was prime contractor for installation of a power cable duct under False Creek in conjunction with the Vancouver City Central Transmission Project.

Directional Drilling

Vancouver City Central Transmission

BC

View Project

Vancouver City Central Transmission

Michels constructed a 63 kilometers of 36-inch from Killam to Hardisty.

Mainline Pipeline

E2H

AB

View Project

E2H

A successful team is a group of
many hands but of one mind

Bill Bethel

We do that.

Contact Us